Remediation contribution orders – a cautionary tale for developers and responsible entities

In the latest instalment of RCO determinations the First-Tier Tribunal has handed down their judgment in Secretary of State v Urban Splash Ltd & Others [2026].

The central question in this case was how to identify a "relevant defect" within the meaning of the Building Safety Act 2022. The FTT also considered who should fund remediation costs; the taxpayer or a 'responsible entity'.

Seven high rise residential buildings in Manchester which were found to be unsafe, with serious fire-safety defects, although the extent of these defects was disputed. Urban Splash, the First Respondent, was the original developer, and a number of other Urban Splash entities were joined in as Associated Persons. The remediation works were carried out at a cost in excess of £60 million, of which £51.5 million was funded by the Building Safety Fund. Crucially, at the time of remediation, Urban Splash no longer owned the buildings and did not contribute to the cost of remediation.

A claim for an RCO was therefore brought by the Secretary of State to recover the sums expended from the Building Safety Fund.

Remediation contribution orders – just and equitable

S.124(2) of the Act provides that an RCO can be ordered for the purpose of meeting costs incurred or to be incurred in remedying "relevant defects" relating to a "relevant building". Under s.124(1) of the Act, the Tribunal must decide whether it is just and equitable to make an order.

'Relevant defects'

S.120 of the Act defines 'relevant defects' as a defect regarding the building that arises as a result of any done/not done, or anything used/not used in connection with relevant works, and, causes a building safety risk.

'Relevant works' accounts for works relating to construction or conversion of a building within the period of 30 years prior to the Act being brought into force. Urban Splash disputed that the works undertaken were 'relevant defects' on the basis that the wrong benchmark for assessing relevant defects was applied, and that there was insufficient evidence the remediation pertained to 'relevant defects'.

'Relevant works' accounts for works relating to construction or conversion of a building within the period of 30 years prior to the Act being brought into force. Urban Splash disputed that the works undertaken were 'relevant defects' on the basis that the wrong benchmark for assessing relevant defects was applied, and that there was insufficient evidence the remediation pertained to 'relevant defects'.

The Tribunal held that they must first identify a 'defect' which they accepted is a broad concept; giving an example of a defect which exists despite complying with Building Regulations at the time of the building's construction/conversion.

Once a defect has been identified, the Tribunal will then consider (a) whether it arises as a result of anything done/not done, or used/not used, in connection with relevant works; and (b) if so, whether it causes a building safety risk.

The Tribunal rejected the argument that a building safety risk is linked to tolerability, confirming that any risk to the safety of people in or about the building arising from the spread of fire or building collapse constituted a building safety risk.

That said, the Tribunal accepted that, in line with the findings in the Edgewater and Canary Riverside cases, the level of risk remains relevant when determining the remediation works required to remedy the defect.

It is also worth noting that the Tribunal found what is 'just and equitable' may be influenced by whether buildings can be shown to have complied with applicable standards in force at the time, albeit most likely only in a case where the ultimate payer is the original developer of the Building Safety Fund.

Judgement

It was held that each of the seven buildings did contain relevant defects in relation to fire safety, and the remediation efforts undertaken by the various landlords and RMC companies were 'reasonable responses' to them. Interestingly, the waking watch costs claimed were excluded because insufficient evidence had been provided to illustrate they were reasonably incurred, in contrast to other RCO decisions.

Urban Splash was therefore ordered to pay a total of £46,500,650 as part of the RCO, with the other five respondents held to be joint and severally liable. The First-Tier Tribunal applied a 10% reduction to the RCO imposed, to accord for a 'just and equitable' result, as per their discretion to do so under s.124(2) of the Act; although, it is important to note that this did not account for the government being 10% liable for the works, for example. It simply reflected a fairer result for the respondents.

The Urban Splash case illustrates that the Tribunal continue to find that developers and associated persons are the first port of call for the payment of remediation works but the quantum of that liability remains open to significant arguments, going to the heart of who was ultimately responsible for the building safety crisis.